Flood damage repair on Rietzschkegrund road 13 to 15

Spielplatz Apothekerpark
Meißner Straße
Speisesaal Lögy
Bauhelme

Flood damage repair on Rietzschkegrund road 13 to 15

vor der Baumaßnahme

nach der Baumaßnahme

Reason and objective

Fundamental expansion of the roadway damaged by storm water, as preliminary work rerouting Rietzschkebach away from the road towards the forest slope, replacement construction of approx. 65 m of DN 800 stream pipework with inlet and outlet structure

Planning

ISTW Ingenieurgesellschaft (road), ACI Ingenieurgesellschaft (stream relocation)

Construction time

July 2019 to December 2019

Construction work

Heinz Lange construction company GmbH

Costs/
Financing

approx. 440,000 €
100% funding by the Federal Republic of Germany and the Free State of Saxony from the 2013 reconstruction aid fund on the basis of the directive of the Saxon state ministries on the granting of subsidies to repair flood damage from 2013
This construction project was co-financed by tax revenue on the basis of the budget approved by the members of the Saxon state parliament.