Occasion and objective Fundamental repair of the traffic system as a measure from the reconstruction plan for flood damage elimination in 2013, complex construction project including stormwater sewer and stormwater retention basin, addition of pavements
Planning ISTW / ACI Ingenieurgesellscahft
Construction time April 2017 to November 2018
Construction work Heinrich Lauber GmbH & Co. KG, Coswig
Costs/
Financing
Construction costs: € 2,700,000 - total costs incl. RW sewer and retention basin
Realisation with the support of the Federal Republic of Germany and the Free State of Saxony from the 2013 reconstruction aid fund and a grant in accordance with the RL KStB

This construction project was co-financed by tax revenue on the basis of the budget approved by the members of the Saxon state parliament