Meißner Strasse between Dr.-Külz-Str. and Rennerbergstrasse
Reason and objective |
Fundamental expansion and rerouting of the motorised individual and public transport systems and all media lines, in particular for the renewal of the combined sewer as the main collector in Radebeul |
Planning |
IVAS Ingenieurbüro für Verkehrsanlagen und -systeme LP 1-4 |
Construction period |
February 2019 until June 2020 |
Construction work |
WOLFF & MÜLLER Tief- und Straßenbau GmbH & Co. KG |
Costs/ financing |
approx. € 5,100,000 Own funds from the district town of Radebeul and 80 % funding as a grant from the Free State of Saxony in accordance with the Municipal Road Construction Directive Part A This construction project was co-financed by tax revenue on the basis of the budget approved by the members of the Saxon state parliament. |