Reconstruction and refurbishment of the Pestalozzistraße branch of the Lößnitzgymnasium grammar school
Occasion and objective | Fire safety upgrading and refurbishment inside the school |
Planning | ADER ARCHITEKTEN from Radebeul |
Construction time | July 2015 to June 2016 |
Costs/ Financing |
Construction costs: € 880,000 Funded via the school infrastructure funding programme (without IT) by the SAB Funding amount/grant: € 314,484.10 |