Extension of August-Bebel-Straße between Schiller- and Goethestraße
![](/radebeulmedia/Bilder/Strassen+und+Pl%C3%A4tze/August_Bebel_Stra%C3%9Fe+zwischen+Schillerstra%C3%9Fe+und+Goethestra%C3%9Fe+vor+Bauma%C3%9Fnahme-height-358-width-450-p-8060.jpg)
© Stadtverwaltung Radebeul
August-Bebel-Straße zwischen Schillerstraße und Goethestraße vor Baumaßnahme
![](/radebeulmedia/Bilder/Strassen+und+Pl%C3%A4tze/August_Bebel_Stra%C3%9Fe+zwischen+Schillerstra%C3%9Fe+und+Goethestra%C3%9Fe+nach+Bauma%C3%9Fnahme-height-338-width-450-p-8344.jpg)
© Stadtverwaltung Radebeul
August-Bebel-Straße zwischen Schillerstraße und Goethestraße nach Baumaßnahme
Reason and objective | Removal of winter damage, road and pavement construction |
Planning | INFRAPLAN MELIOR GMBH, independent consulting engineers, Dresden |
Construction period | March to May 2014 |
Construction work | Hentschke Bau GmbH, Dresden |
Costs/ Financing |
Construction costs: € 166,000 Proportionate allocation from the emergency road programme for winter damage repair |