Changes to the traffic routing in the course of the construction work After the Schiffsmühle

27.05.2022

As part of the new S82 Meißner Straße roundabout construction project, there will be changes to the traffic routing at Lößnitzstraße (Coswig) and at the entrance to the Megadrome.

The measure is being carried out in preparation for the future connection "Nach der Schiffsmühle" and will be realised in three construction phases.

Phase 1 from 01.06. to 29.06.2022 as a half-sided closure with traffic lights. The Lößnitzstraße access road between Am Mittelfeld and Meißner Straße will be fully closed.

Phase 2 is expected to run from 30 June to 17 July 2022, also as a half-sided closure with traffic lights. The Megadrome access road will be provisionally constructed and can only be reached via Coswig.

Phase 3 expected from 18/07 to 27/08/2022 as a complete closure. The diversion will be via: Dresdner Straße - Am Güterbahnhof - Kötitzer Straße - Grenzstraße - An der Walze - Friedrich-List-Straße - Kötitzer Straße - S84 - Cossebauder Straße - Meißner Straße