Meißner Straße construction progress
19.04.2024
Work on the first construction section between Schillerstraße and August-Bebel-Straße/Zinzendorfstraße is in its final phase. The carriageway, footpaths and bus stop areas along Meißner Straße have largely been completed. The traffic lights at the Meißner Straße/August-Bebel-Straße/Zinzendorfstraße junction have been installed. Until the opening to traffic, which is scheduled for the end of April, pavements and carriageway surfacing will be installed in the roads leading into the junction, road markings will be applied and adjustments will be made to the verges.