Altlindenau - Dippelsdorfer Straße

Spielplatz Apothekerpark
Meißner Straße
Speisesaal Lögy
Bauhelme

Altlindenau - Dippelsdorfer Straße

Vor der Baumaßnahme

Nach der Baumaßnahme

Cause and goal

Disabled access to the bus stop

Planning

Engineering office W Plus from Dresden

Construction time

October to November 2020

Construction work

STRABAG AG Saxony Directorate - Meißen Group
Costs/
financing

approx. 50,000 €
Own funds of the district town of Radebeul and 90% share of public transport funding
This construction project was co-financed by the ZVOE.