Heinrich-Zille-Straße between Rosa-Luxemburg-Platz and house no. 20
![](/radebeulmedia/Bilder/Strassen+und+Pl%C3%A4tze/Heinrich_Zille_Stra%C3%9Fe+vor+Bauma%C3%9Fnahme-font_size-normal-height-358-width-450-p-20012732.jpeg)
© Stadtverwaltung Radebeul
Heinrich-Zille_Straße vor Baumaßnahme
![](/radebeulmedia/Bilder/Strassen+und+Pl%C3%A4tze/Heinrich_Zille_Stra%C3%9Fe+nach+Bauma%C3%9Fnahme-font_size-normal-height-290-width-387-p-20012730.jpeg)
© Stadtverwaltung Radebeul
Heinrich-Zille-Straße nach Baumaßnahme
Reason and objective | Fundamental repair as a precautionary measure for the expansion of Meißner Straße (diversion route), coordinated realisation with the media providers, in particular new construction of the combined sewer |
Planning | W Plus Büro für Ingenieurdienstleistungen, Dresden |
Construction time | July 2017 to March 2018 |
Construction work | Heinrich Lauber GmbH & Co. KG Coswig + Strabag AG, Meißen |
Costs/ Financing |
Construction costs: approx. 445,000 € Proportionate funding for municipal road construction RL KStB This construction project was co-financed by tax funds on the basis of the budget approved by the members of the Saxon state parliament |