Expansion of Winzerstraße between Borstraße and Schuchstraße

Spielplatz Apothekerpark
Meißner Straße
Speisesaal Lögy
Bauhelme

Winzerstraße between Borstraße and Schuchstraße

Winzerstraße vor Baumaßnahme

Winzerstraße nach Baumaßnahme

Occasion and objective Supplementary basic repair of carriageway and footpaths with sewer construction by WSR, cooperation of media carriers
Planning ACI
Construction period August 2016 to March 2017
Construction work Heinrich Lauber GmbH & Co. KG, Coswig
Costs/
Financing
Construction costs: approx. 254,000 €
Own funds of the large district town of Radebeul